MINUTES REGIONAL SCHOOL DISTRICT 10 BUILDING COMMITTEE MEETING December 19, 2006
Members Present: Dave Dickson, Dave Lenihan, Paul Omichinski, Ron Sadecki, Lisa Sadler
Absent: Dave Fortin, Durwin Jones, Paula Schwartz, Peter Surveski, Peter Turner
Also Present: Chuck Boos - KBA Alan McIlveen, Walter McIlveen & Associates Ken Hunt - O & G Construction
I. Call To Order The Building Committee meeting was held at the Administrative Office, and was called to order at 7:05 pm by Chairman Paul Omichinski.
II. Approval of Minutes Minutes from the November 21, and December 5, 2006 meetings could not be approved due to lack of quorum.
III. Old Business · Project status - K. Hunt distributed the November 2006 monthly status report. The construction budget is $44,971,562, and project is 79% completed. Contingency is at $283,935. The change orders discussed, and presented for approval, are as follows:
C.M. # Description Amount Colossale Concrete 00112 H.S. front entrance site modification $ 5,040
Joe Capasso Masons 00194 Relocate door E150 $ 2,686 backcharge to HHS Mechanical 00195 Masonry infill “J” stairs for window opening $ 4,826 00200 Patching allowance increased $24,030
Burlington Construction 00197 Lintels at “F” below new windows $ 1,183
S. G. Milazzo Co. 00190 Drywall back charges $ 1,843 backcharge to Comfort
Food Service 00216 Mixer credit (1,000)
Otis Elevator 00181 Elevator operator “E: $ 750
Fine Painting 00210 Paint M.S. gym ceiling $ 6,440 * Page 2 December 19, 2006
Comfort Systems 00190 Wiring tempered water valve ($1,036) backcharge from C&H 00190 Corridor “A” coordination ($3,287) backcharge from Modern 00190 Drywall Work ($1,843) backcharge from S.G. Milazzo
Modern Mechanical 00190 Corridor “A” coordination $3,287 backcharge to Comfort
HHS Mechanical 00194 Relocate door E150 ($2,686) backcharge from Capasso
C & H Electrical 00201 D 127 sub panel $ 6,486 00077 Lens covers for gym lights $ 2,411 00204 “D2” dimming ballasts $ 2,741 00190 Wiring tempered water valve $ 1,036 backcharge to Comfort 00205 Fume hood switches/receptacles $ 1,399 00175 MS area of refuge master station $ 884 00203 Relocate feeder in way of RTU37 $ 850 *
* These change orders were put on hold pending further follow-up by K. Hunt and not approved at this time.
Change orders could not be approved due to lack of quorum. D. Lenihan will ask for vote via email.
· Cost and schedule update D. Lenihan distributed list of soft costs. Line items that might yield additional monies for contingency were discussed including the $494,860 cost for furniture and equipment. Committee will ask D. Fortin for more information on that line item. John Deeb, music director had submitted list of musical instruments for purchase. P. Omichinski will meet with him to discuss items on the list.
· Review and approval of project invoices, bids, etc. - List of invoices for payment are:
Date Vendor % complete Amount 11/28/06 KBA base contract CA 66% 20,194.51
11/30/06 O&G Nov. billing 73% 206,816.00 11/30/06 Colossale Concrete Nov. billing 84% 33,739.25 11/30/06 McCarthy Concrete Nov. billing 99% 1,357.55 11/30/06 United Steel 94% 0.00 11/30/06 Haz Pro 73% 0.00 11/30/06 Capasso (mason) Nov. billing 97% 46,663.92 11/30/06 Burlington Constr. Nov. billing 62% 243,125.45 11/30/06 Silktown Roofing Nov. billing 73% 99,189.30 11/30/06 Cherry Hill Glass Nov. billing 80% 59,750.00 Page 3 December 19, 2006
11/30/06 Millazzo (drywall) Nov. billing 91% 47,011.27 11/30/06 Conn Acoustics Nov. billing 45% 7,980.00 11/30/06 Pro-Tect, Inc. (fire spray) 40% 0.00 11/30/06 Barall & Konover Carpet Nov. billing 76% 47,301.68 11/30/06 Barall & Konover Tile Nov. billing 58% 5,225.00 11/30/06 Fine Painting Nov. billing 70% 14,725.38 11/30/06 Otis Elevator 53% 11,757.00 11/30/06 Warehouse Store Fixt. Nov. billing 99% 38,653.60 11/30/06 Comfort (plumbing) 79% 0.00 11/30/06 HHS (fire protection) Nov. billing 76% 49,562.45 11/30/06 Modern Mechanicals Nov. billing 74% 264,029.00 11/30/06 C&H (electrical) Nov. billing 86% 90,895.00 11/30/06 Independent Testing thru Sept. 3,885.00 EnviroScience abatement monitoring through 10/06 3,320.00 Total $1,295,181.35
Invoices could not be approved due to lack of quorum. D. Lenihan will ask for vote via email
· Next steps R. Sadecki has not yet received response to his April 2006 correspondence. Indicated he had also submitted several more in the last month and has not received responses.
Cost for bubbler attachments in the 5th grade wing classroom sinks are still pending.
IV. Adjourn Meeting ended at 9:10 pm. Next Building Committee Meeting is scheduled for January 9, 2007 (revised from January 2, 2007) at 7:00 pm at Central Office.
|