Building Project

 

TENTATIVE TIMELINE FOR THE BUILDING PROJECT

AS OF 3/15/04

The following schedule is tentative and conservative. We will modify it as more details become available.

 

Tentative Pre-Construction Schedule  
   

Develop Schematic Design Drawings

February-May 2004

Develop Design Development Drawings

May-August 2004

Submit to Burlington Wetlands Commission

July 2004

Develop Working Drawings

August-December 2004

Phase I State and Local Approval

October-December 2004

Phase I Bid and Award

December-February 2005

Phase II State and Local Approval

December-February 2005

Phase II Bid and Award

February-April 2005

 

 

Tentative New Construction Schedule

 

 

 

Auditorium

February 2006-August 2006

Cafeteria/Kitchen/Gym

February 2005-February 2006

Media Center/5th Grade wing

April 2005-June 2006

Shared wing

April 2005-April 2006

Lewis Mills Wing

May 2005-May 2006

Renovation Work

April 2005-August 2007

 

 

 

Back to Building Project Main Page

 

 