Building Project
TENTATIVE TIMELINE FOR THE BUILDING PROJECT
AS OF 3/15/04
The following schedule is tentative and conservative. We will modify it as more details become available.
Tentative Pre-Construction Schedule Develop Schematic Design Drawings
February-May 2004
Develop Design Development Drawings
May-August 2004
Submit to Burlington Wetlands Commission
July 2004
Develop Working Drawings
August-December 2004
Phase I State and Local Approval
October-December 2004
Phase I Bid and Award
December-February 2005
Phase II State and Local Approval
December-February 2005
Phase II Bid and Award
February-April 2005
Tentative New Construction Schedule
Auditorium
February 2006-August 2006
Cafeteria/Kitchen/Gym
February 2005-February 2006
Media Center/5th Grade wing
April 2005-June 2006
Shared wing
April 2005-April 2006
Lewis Mills Wing
May 2005-May 2006
Renovation Work
April 2005-August 2007